Case
History 4
|
|
|
Location of Work: Nutley, New Jersey Scope of Work: Excel was contracted to complete the project after a Preliminary Assessment(PA) was initiated by the previous consultant. Based on the results of the PA, the NJDEP's primary concern was soil contamination below the facility foundation and the potential for deep aquifer contamination. Following are the key project aspects.
Project Outcome: As an alternative to the excavation and treatment of soil, Excel was able to establish a DER for the residual soil concentrations at the site using the existing building foundation as the cap. In addition, a groundwater investigation was avoided by utilizing available information avoiding installation of groundwater monitoring wells. As a result, project related costs were drastically reduced during the investigative phase of work. In addition, even greater project cost savings were realized by application of institutional controls in lieu of active remediation. |
|